Stuttgart 21 is a major railway and urban development project in Stuttgart, Germany, which replaces the surface railway lines with tunnels. It forms part of the Stuttgart–Augsburg railway and the Main Line for Europe, linking Paris and Vienna within the Trans-European Networks. Its centrepiece is an underground Stuttgart Hauptbahnhof, supported by about 57 kilometres of new railways. The project has been highly controversial because of the demolition of older structures, large construction areas, high costs and long delays.
Concept and scope



The project combines plans for high-speed links from Stuttgart to other cities with improvements to local infrastructure. The existing 16-track terminus is to be replaced by an underground station with eight through platforms. New tracks will run below ground at right angles to the northern end of the current building, and parts of the historic Bonatzbau, along with the platforms and approach tracks, are to be demolished. The Filder Tunnel would connect the new station to a Filder station serving the airport and trade fair grounds, and then to the Wendlingen–Ulm high-speed line.
Costs and opposition



Construction began in February 2010, and total cost estimates have risen considerably over time, reaching €9.15 billion by 2022. The plan was opposed from its early stages, with demonstrations, a petition that gathered 67,000 signatures, and debate over whether a local referendum could decide the matter. Critics proposed renovating the existing station, while supporters pointed to the wider rail benefits. Opening dates have been repeatedly postponed, with the new station now scheduled for December 2031.