Oil shale-fueled power plant in Jordan

Attarat Power Plant

Key facts

instance ofthermal power station
countryJordan
located in the administrative territorial entityAmman Governorate
All data from the card 15
Country
Jordan
Location
Attarat Umm Ghudran
Coordinates
31°16′08″N 36°26′52″E / 31.2689°N 36.4477°E
Status
Commissioned
Construction began
16 March 2017
Commission date
25 October 2022 (Unit 1) 26 May 2023 (Unit 2)
Construction cost
2.1 Billion USD
Owners
YTL Power International (45%)Guangdong Energy Group Co., Ltd. (45%)Eesti Energia (10%)
Operator
Attarat Power Company
Primary fuel
Oil shale
Units operational
2 X 235 MW
Make and model
Siemens
Units planned
2 x 235 MW (net)
Nameplate capacity
470 MW
Website
attaratpower.com.jo

Attarat Power Plant is an oil shale-fueled power plant constructed in the Attarat Umm Ghudran area, 50 kilometres (31 mi) east of Al Qatranah, in Jordan. The project is developed by the Attarat Power Company (APCO), a partnership between YTL Power International (45%), Guangdong Energy Group Co., Ltd. (45%) and Eesti Energia (10%). It is the first oil shale power plant in Jordan and the largest private sector project in Jordan to date.

History

The project was originally developed by an Estonian power company Eesti Energia (Enefit). The concession agreement between the Ministry of Energy and Mineral Resources and National Electricity Power Company of Jordan, and Eesti Energia was signed on 30 April 2008. In 2010, YTL Power International bought a 30% stake in the project.

A 30-year power purchase agreement (PPA) was signed with Jordan in October 2014. The construction agreement was signed on 12 January 2016. The financial closure agreement was signed on 16 March 2017. At the same time, YTL Power International increased its stake in the project up to 45% and Guangdong Energy Group Co., Ltd. became a new shareholder also with 45% stake. Construction started shortly after.

Technical description

The power plant has 554 MW (gross) and 477 MW (net) capacity. It will consist of two circulating-fluidized-bed units.

The power plant consumes 10 million tons of oil shale per year which will be provided from the nearby open-pit mine and it is also the biggest mine in Jordan. Over its 40-year lifetime it would need an oil-shale mining area of approximately 11 square kilometres (4.2 sq mi).

The plant is among the largest power plants in Jordan (the largest being Aqaba Thermal Power Station), and the largest oil shale-fired power plant in the world after Narva Power Plants in Estonia.

Financing

The project costed US$2.1 billion. Shareholders will invest $528 million and the rest will be financed by $1.6 billion loan provided by the Bank of China and the Industrial and Commercial Bank of China, and guaranteed by China Export and Credit Insurance Corporation. This is the largest private project financing supported by China Export and Credit Insurance Corporation to date.

Construction

The plant is designed by WorleyParsons. The engineering, procurement and construction contract was awarded to Guangdong Power Engineering Corporation, a subsidiary of China Energy Engineering Group. The power plant would be designed by WorleyParsons. It would use boilers provided by Foster Wheeler, and the turbine and generator by Siemens.